TfL Overground Programme

London Overground Capacity Improvement Programme

Value  

£324m

Period

2013-17

Transport for London (TfL)The London Overground Capacity Improvement Programme was a complex urban rail upgrade programme involving the East London Line and North London Line.

PACE was appointed to provide programme management and recovery support, helping London Overground establish the structure, controls, technical integration, and delivery capability required to successfully deliver the programme.

Value : £324

Period : 2013–2017

Client : TfL
Programme : LOCIP

images (7).jpg

THE PROJECT

A Critical Rail Infrastructure Programme

PACE was contracted to undertake the role of programme Management for the recovery of both the East London Line, and North London Line components of the 5 car upgrade programme. The programme value was £324m, and involved all the complexities expected from a major infrastructure systems based urban upgrade programme.

THE CHALLENGE

A Programme Under Severe Time Pressure

The programme came under pressure from the outset with a mayoral commitment that effectively removed one year from the baseline programme from the Overground team. The programme challenge was coupled with structure and procurement of a new set of suppliers, either lacking experience or commercially challenged to deliver this unique scheme of upgrades.

PACE was contracted to solve these problems, working as an integrated part of the overground team and its commercial and technical partner organisations to solve the significant challenges faced by the programme board.

20-september-2024-indonesian-railways-kai-passing-through-tracks-city-jakarta.jpg
railroad-tracks-city-against-cloudy-sky-dusk.jpg

WHAT WE DID

Taking Control. Creating Momentum.

Creating Structure. Strengthening Delivery.

PACE began by establishing a clear understanding of the programme baseline and identifying where the existing structure and delivery approach needed to change.

Improving Design Integration
 

Processes were introduced to strengthen design integration and enable live information sharing across the programme.

Key systems engineers were embedded within the programme to improve technical coordination and decision-making.

Reframing the Work Packages
 

We restructured work packages and management focus to improve accountability, clarify responsibilities, and maximize delivery potential.

 

Building Stronger Delivery Teams

PACE worked closely with delivery organizations to strengthen management capability and ensure that the right expertise was aligned with each work package.

On the North London Line, PACE worked with Laing O'Rourke to restructure the project management team and site logistics

Strengthening Programme Controls

Working with Anglia Route, we developed an access strategy that secured almost every weekend with 52-hour access, alongside two major seven- and nine-week blockades incorporated into the longer-term programme.​​

images (15).jpg

WHAT ARE ACHEIVED

Quality-Assured Expertise for Complex Schemes

Embedded project controls, processes, organisational enhancement and effective reporting to London Overground and LOROL to ensure effective programme Management

Working closely with Cleshars and CH2M, providing enhanced management and technical support to allow a tier 2 Main contractor organisation (at the time) to deliver a very complex project

On the North London Line working closely with Laing O’Rourke to plan and restructure the project Management team and site logistics to ensure to delivery plan was achievable in a constrained environment, and also re-contracting packages of work to ensure delivery competence was effectively assigned.

Implementation of an effective cross programme communication  and stakeholder management structure and reporting processes, optimising honesty and accuracy of information as well driving  solid support for the supply chain, creating a successful team ethos;

Both the East London and North London Line programme were delivered on time and within budget, culminating in the programme being awarded the ICE engineering award.